Project Profiles
- Design and build of a continuous electrically heated 50 kg/h pyrolysis kiln for charcoal production)
- 250 kWe/ 250-500 kWth biomass gasification CHP, Biomass Engineering Ltd., Mossborough Hall, England (2002-2005)
- 60-80 kg/h test biomass and waste gasifier coupled to a Capstone micro gas turbine, Newton-le-Willows, England (2002-2004)
- 300 kg/h and 2000 kg/h (2 MWe) pyrolysis plant for char and CHP production, B.E.S.T. Australia (2005-2007)
- Cost-benefit analysis of encroachment bush removal in Namibia (2008-2009)
- 2002-2004: Effective Cr(III) recovery by gasification with heat production, Pittards PLC and Biomass Engineering Ltd., UK
- Integrated SOx/NOx and particulate removal in coal/olive wastes and leather wastes combustion in a 3.5 MWth plant, Spain (2001-2005)
- 250 kg/h biomass fast pyrolysis plant for power generation, Wellman Process Engineering Ltd., Oldbury, England (1998-2002)